Keep up to date with how projects are going, and understand the process so far. New events will be added as the project progresses.

1 March 2018: Wellington City Councillors expected to consider and potentially approve upgrade plans More Less

Wellington City Councillors expected to consider and potentially approve upgrade plans for Evans Bay Parade, Kilbirnie and Miramar.

1 November 2017: Planned consultation on the traffic changes (resolutions) required to carry out work More Less

Planned consultation on the traffic changes (resolutions) required to carry out work on Evans Bay Parade, and roads in Kilbirnie, Miramar, Strathmore Park, Seatoun and Newtown.

2 October 2017: Consultation closes on the Miramar Avenue traffic changes (resolutions) More Less

Consultation closes on the traffic changes (resolutions) proposed to create a new two-way section of cycleway on Miramar Avenue between the intersection of Shelly Bay Road and Tauhinu Road. This includes replacing the Tauhinu Road roundabout with traffic lights.

17 September 2017: Public feedback period closes More Less

Public feedback period closes on:

·   Miramar Avenue phase 2 (Tauhinu Road to Park Road)

·   Kilbirnie roads and connections to Newtown

·   Miramar roads and connections to Strathmore Park and Seatoun

·   Evans Bay Parade – Cobham Drive to Carlton Gore Road

6 September 2017: Open day More Less

Open day at ASB Sports Centre for people to find out more about proposed options in the east and provide their thoughts and suggestions.

6 September 2017: Second open day More Less

Second open day at ASB Sports Centre on the proposed design options for the eastern suburbs.