Thorndon Quay has been divided into 13 areas for construction. We will generally be working in two areas at any given time.
Area 1 - Bunny St intersection to Mulgrave St
Timing tbc, early 2025
Area 2 - Mulgrave St intersection
Day works currently underway, scheduled to finish February 2025
Area 3 - In front of National Archives and Capital Gateway exit
To be completed this sealing season (Oct 2024 - May 2025), exact timing tbc
Area 4 - Pipitea Marae to Resene building
Road sealing is complete. Cycleway delineator install and cycleway sealing to be complete early December 2024
Area 5 - Resene building to Davis St
Road sealing is complete. Cycleway delineator install and cycleway sealing to be complete early December 2024
Area 6 - Davis St to Sebel Hotel
Night works currently underway. Day works scheduled to start early December 2024
Area 7 - Sebel Hotel to Wattyl Paints
Sealing to be done once day works in Area 6 are completed
Area 8 - Wattyl Paints to Carpet Court
Day works finished. Sealing to be completed early December 2024
Area 9 - Curtain Studio to Ramset
Redesign works underway due to removal of raised safety platform. Sealing to be completed early December 2024
Area 10 - Ramset to Tinakori Rd
Sealing to be completed early December 2024
Area 11 - Tinakori Rd intersection
Day works currently underway, scheduled to finish March 2025
Area 12 - Sar St to NZCT
Area complete
Area 13 - Gun City
Area complete
Cycleway separators
We are currently installing cycleway separators as we complete surfacing. Due to this there will be periods where sections of the cycleway will be unpaved