Construction update

21 November 2024

Thorndon Quay has been divided into 13 areas for construction. We will generally be working in two areas at any given time.A map of Thorndon Quay showing that it is divided into 13 areas.

Area 1 - Bunny St intersection to Mulgrave St

Timing tbc, early 2025

Area 2 - Mulgrave St intersection

Day works currently underway, scheduled to finish February 2025

Area 3 - In front of National Archives and Capital Gateway exit

To be completed this sealing season (Oct 2024 - May 2025), exact timing tbc

Area 4 - Pipitea Marae to Resene building

Road sealing is complete. Cycleway delineator install and cycleway sealing to be complete early December 2024

Area 5 - Resene building to Davis St

Road sealing is complete. Cycleway delineator install and cycleway sealing to be complete early December 2024

Area 6 - Davis St to Sebel Hotel

Night works currently underway. Day works scheduled to start early December 2024

Area 7 - Sebel Hotel to Wattyl Paints

Sealing to be done once day works in Area 6 are completed

Area 8 - Wattyl Paints to Carpet Court

Day works finished. Sealing to be completed early December 2024

Area 9 - Curtain Studio to Ramset

Redesign works underway due to removal of raised safety platform. Sealing to be completed early December 2024

Area 10 - Ramset to Tinakori Rd

Sealing to be completed early December 2024

Area 11 - Tinakori Rd intersection

Day works currently underway, scheduled to finish March 2025

Area 12 - Sar St to NZCT

Area complete

Area 13 - Gun City

Area complete

Cycleway separators

We are currently installing cycleway separators as we complete surfacing. Due to this there will be periods where sections of the cycleway will be unpaved