Thorndon Quay has been divided into 13 areas for construction. We will generally be working in two-three areas at any given time.
Area 1 - Bunny St intersection to Mulgrave St
Timing tbc, early 2025
Area 2 - Mulgrave St intersection
Day works currently underway, scheduled to finish February 2025
Area 3 - In front of National Archives and Capital Gateway exit
To be completed this sealing season (Oct 2024 - May 2025), exact timing tbc
Area 4 - Pipitea Marae to Resene building
Moore Street raised crossing to be completed, exact timing tbc
Area 5 - Resene building to Davis St
Cycleway delineators install and cycleway sealing currently underway, to be completed early December 2024
Area 6 - Davis St to Sebel Hotel
Day works scheduled to begin early January 2025
Area 7 - Sebel Hotel to Wattyl Paints
Sealing to be completed once Area 6 day works have finished
Area 8 - Wattyl Paints to Carpet Court
Day works finished. Sealing currently underway, to be completed early December 2024
Area 9 - Curtain Studio to Ramset
Redesign works complete. Sealing currently underway, to be completed early December 2024
Area 10 - Ramset to Tinakori Rd
Sealing currently underway, to be completed early December 2024
Area 11 - Tinakori Rd intersection
Day works currently underway, scheduled to finish March 2025
Area 12 - Sar St to NZCT
Area complete
Area 13 - Gun City
Area complete
Surfacing & Cycleway Information
We are currently installing cycleway separators as we complete surfacing. We will leave a 1.5 metre strip next to the pavement, so the cycleway can still be used. Once the cycleway separators have been installed, we will then complete the surfacing of the cycleway.
During this time, there will be some carparks coned off in the day. This is to ensure the parks are free for the evening and there are no delays with the surfacing work at night. These spots are available to park in during the day, but they need to be vacated by 7pm to avoid being towed.