Project timeline and construction updates

Keep up to date with how the project is going, and understand the process so far. New information will be added as the project progresses.

15 January 2025: Hataitai beach seawalls More Less

A section of  seawall by and to the south of the Hataitai beach changing rooms and toilets is to be replaced. Work is expected to start in early 2025 (dates to be confirmed).  The work does not include the section of wall adjacent to the boatsheds.

 The low wall at the rear of Hataitai beach will also be replaced. This will happen in two stages once work on the seawall is complete. It's likely the work at the beach will start in autumn and continue through the winter. The changing sheds and toilets will be open as usual, and it will always be possible to swim at and use the beach.

30 November 2024: Completion of the section Little Karaka Bay to Weka Bay More Less

The work on the new seawalls, pedestrian crossings and safer bike and walking paths between Little Karaka Bay and Weka Bay is nearly finished and expected to be complete by the end of November 2024.

April 2023: Construction starting - Little Karaka Bay to Weka Bay More Less

Construction work on the section between Little Karaka and Weka bays will get under way from 11 April. Our contractor Downer will start at Weka Bay to build the new walking and biking paths, where the previously completed paths end. They will work back towards Little Karaka Bay.

Read more

24 November 2021: Council approves concept design and traffic resolutions with some changes More Less

Pūroro Āmua, the Council's Planning and Environment Committee, approved the concept design for the section between Cobham Drive and Greta Point with some changes, and agreed the project should proceed. Some changes to the concept design were made following suggestions and concerns raised during consultation. More information on the decision is available in:

15 October 2021: Consultation closed - Greta Point to Cobham Drive More Less

Thanks for all your feedback, the consultation is now closed.

Councillors will make decisions on whether the project should go ahead in November 2021.

Read more

14 September 2021: Consultation starts on the section between Greta Point and Cobham Drive More Less

Now's the time to have your say on the proposed draft designs for Evans Bay Parade, from Greta Point to Cobham Drive. Consultation will run for just over four weeks, closing on 14 October.

Due to Covid alert levels, instead of community drop-in sessions we are holding two online webinars on 21 and 29 September so people still get the chance to hear about the project and ask questions:

 

 

Read more

6 April 2021: Work in Weka Bay getting under way More Less

Construction work on the new walking and bike paths will extend around the corner into Weka Bay from this week.

The contractors have some finishing work still to do in Kio Bay so there will be construction activity continuing there too. Weather permitting, the bike path through Kio Bay is expected to be asphalted in mid-April. A new pedestrian crossing will be installed in Kio Bay once the lights, which are on order, arrive. Unfortunately, there are still some Covid-19-related supply chain issues and delays. We hope this work will happen in June but can't confirm that yet. 

The work in Weka Bay will extend part way around the bay. As has happened in other areas, the contractors will first mill and remove the existing surfacing along the edge of the road and footpath edge and then lay the new kerbline. They will then lay the new concrete footpath and develop the new seaward side bus stop, which will be slightly south of the existing bus stop.

The parking on the seaward side opposite numbers 140 to 170 Evans Bay Parade will be cordoned off from Friday 9 April so this can happen.

There will be construction fences, diggers, and other heavy vehicles to accommodate – and we need to prioritise people on foot and bikes, and through traffic.

If you have a vehicle parked here, please shift it by Friday. If it still parked here on 9 April, the contractors will need to get it moved to a safer spot. Our Contact Centre staff will be able to tell you where it has been moved to. They are available 24/7 on 04 499 4444 and will just need your registration number.

The parking on the seaward side of the road (opposite numbers 140 to 170 Evans Bay Parade) is being permanently removed to provide more space for people using this busy commuter and recreational route. Separate walking and bike paths and the new bus stop will be developed her